The reconstruction of heating main in the city centre started

25.05.2015

The reconstruction of heating main in Entuziastov Street is one of the most important projects for Interpolis in 2015.

The heating main is situated in the city centre under main traffic artery surrounded by dense residential development. The company specialists shall lay about 1200 metres of 500 mm pipes in two-pipe design under roadway under constraints of numerous crossings with other communications among them telecommunications, electrical network, gas pipelines, water pipes, sewerage.

Dates of work are May, 19 - September. 1. Time duration is connected not only with huge amount of work. First of all it is connected with stage-by-stage approach as it is impossible to stop traffic on busy street in the centre of Chelyabinsk. Meanwhile residents of surrounding houses and social objects will be supplied with hot water by means of temporary heat pipeline.

Schedule and stages of works including decisions about traffic closing strongly agree with the City Administration. At the first stage the company found a way to leave one lane in each direction for the movement of vehicles. At night, as an additional security measure for residents’ safety, the construction site is illuminated with LED lamps.