Campaign for overhaul of heating district started

30.05.2015

More than 100 projects shall be done in a summer period by Interpolis Company under overhaul program.

Capital repair of heating networks started from May, 16 together with hydrostatic testing. First of all 8 most problem sites with high accident rate were reconstructed. Among them the longest pipeline section (more than 300 meters) was reconstructed. It provides with heat tens of housing blocks in Chelyabinsk.

To Interpolis specialists’ credit, Chelyabinsk residents didn't feel any discomfort. All works for tie-in of new pipe sections were done in a period less than 24 hours.

At the moment reconstruction work is in progress all over the city. Most of the heat pipelines to be repaired are situated inside residential districts, but some of them are under main traffic arteries and in symbolic places of the city. So, the company will lay heating main under Engels Street and reconstruct pipe section next to the City Administration.